Common Grounds Improvement - May 14, 2012
The project to stop the erosion of the common grounds behind the houses has started. Monstrosity Tree Service has taken out 44 stumps that are left from previous tree removal and have only 4 left to remove.
The next phase is the clean up of the commons which is scheduled to start on May 21 and will take about two weeks. The following phase will be the rock placement starting on June 4 th and may take three weeks. We should be complete before the monsoons start.